35,000 tons of ore have been extracted at Jeruy, start-up operations are underway

04.02.2020

From November to January of this year, 35 thousand tons of ore were mined and stockpiled at the Jeruy deposit with an average gold grade of 1.85 grams per ton. Meanwhile, construction and installation work is being completed, and the commissioning is underway.

On completion:

  • installation of metal structures, fences and steel plates of the Main building of the Mill, the Thickening and leaching section, and the Crushed ore warehouse;
  • installation of the main process equipment, piping in workshops;
  • Central assay laboratory and Administrative and household complex (decoration works are in progress);
  • engineering networks of the industrial site, which include 3 transformer substations, the system of industrial and firefighting water supply, as well as heat and sewage networks (80% readiness);
  • tailings storage facility (95% readiness).

All work is on schedule.