Works on the site in November 2018

The construction of the Central Checkpoint (contractor – Decor LLC) is nearing completion. With the establishment of the gold mining company's checkpoints, the surrounding cattlemen have become more secure – no uninvited guests come to the pastures anymore.

At the Mill's substation with 110/35 kV overhead line, Electrosila is finishing commissioning work. The facility will be commissioned by the end of 2018.

Enclosed storage of equipment and materials was built by the contractor Arlan LLC.

The contractor, Emark Group LLC, is finishing work on the water intake structures site (mark 1850). Drinking water supply will be provided from December 15.

At the 2700 mark, the construction of a shift camp for the mining complex is underway under the efforts of the contractor, OJSC Kantskaya PMK No. 1.

The construction of the fuel and lubricants warehouse site with the capacity of 600 tons was completed (contractor – Baden Service LLC).

By the end of 2018, the commissioning and start-up of the BIB boiler house and heating networks (contractor – Asia Water Build LLC) will be accomplished.

The road serpentine leads to the industrial site of the quarry (mark 3500), a power line has already been extended there.

All of the contracting companies that carry out construction and installation work on the deposit are Kyrgyz, and all taxes are paid to the state budget.