Work continues on the construction of the processing complex at the Jeruy production site. The pictures show:
- Main facility of the Mill
- Thickening and leaching area
- Weightbridge
- Large crushing body
- Crushed ore storage gallery
- Electrolysis and melting body
- AD-5 intrasite road
- Tailings dump site
- Central assay lab
- The HTS and reagent base warehouse. Contractor Baden Service
- Construction of the maintenance shop
- Construction of a shift camp at the mining and processing complex
- The Mill substation with a 110/35 kV overhead line. Electrosila LLC. The facility was submitted to the State Commission
- Interplot power supply. Upper cluster (LC) of the 35/6 kV MSS with 6 kV overhead lines in the size of 35 kVl. Contractor Mekhkolonna CESS. The work on the site has been completed
- Interplot power supply. Нижний кластер. The lower cluster. 6 kV overhead line. Contractor Electrosila. The facility was submitted to the State Commission
- Reconstruction of the 110/35/10 kV substation in Chat-Bazar. Contractor NK Energo. Reconstruction is completed, the facility was submitted to the State Commission
- Construction of the central checkpoint with a parking lot. Contractor Decor